A 5×5 risk matrix combines five likelihood levels with five severity levels. It helps teams discuss priorities using a defined method. The score supports judgement; it does not replace task knowledge, competent assessment or verification of controls.
Define the scales before scoring
Risk score = likelihood × severity. A result can range from 1 to 25. Define what each level means for your organization, including the exposure period, affected people and consequences. Avoid assigning numbers without shared definitions. Consider credible worst-case consequences rather than only the outcome of a previous incident.
| Level | Illustrative likelihood | Illustrative severity |
|---|---|---|
| 1 | Rare under the defined exposure conditions | Minor harm |
| 2 | Unlikely | Limited injury or impact |
| 3 | Possible | Significant injury or impact |
| 4 | Likely | Major or permanently disabling harm |
| 5 | Almost certain | Fatal or catastrophic consequences |
These descriptions are illustrative. Your approved methodology must define severity and likelihood for the activities and consequences being assessed.
Risk bands and escalation
The calculator uses 1–4 as low, 5–9 as medium, 10–16 as high and 17–25 as critical. ISO 45001 does not prescribe these thresholds or require a 5×5 matrix. Define acceptance and authorization rules explicitly. A low-likelihood, potentially fatal event may need special escalation even when its numerical score falls into a lower band.
Try your own values
Initial and residual risk calculator
Risk score = likelihood × severity. Reassess after controls have been implemented and verified.
Residual risk remains high. Review controls before proceeding under your organization's methodology.
Example bands: 1–4 low, 5–9 medium, 10–16 high, 17–25 critical. These are illustrative, not ISO 45001 thresholds. Training or PPE does not automatically justify reducing severity.
A practical assessment sequence
- Define the activity, boundaries, people and operating conditions.
- Identify hazards, including non-routine work and changes.
- Record existing controls and assess risk under the chosen initial-risk convention.
- Select additional controls using the hierarchy of controls.
- Assign owners, resources, dates and verification evidence.
- Reassess residual risk after controls are implemented and verified.
- Obtain the required authorization and review after relevant changes or incidents.
Some methodologies use “initial risk” before all controls, while others mean risk before proposed additional controls. State the convention clearly. Do not compare assessments based on different conventions as if they were identical.
Residual risk: a worked example
For an illustrative fall-from-height scenario, likelihood 4 and severity 5 give a score of 20. After effective controls are implemented and verified, an assessment might justify likelihood 2 while severity remains 5, giving 10. Under the example bands, residual risk is still high. It therefore requires further consideration under the organization’s acceptance rules.
Do not reduce severity simply because training or PPE has been added. Reassess the actual consequences the controls prevent or mitigate, and record the reasoning. A proposed control that has not yet been implemented is not evidence of reduced residual risk.
The hierarchy of controls
Consider elimination first, then substitution, engineering controls, administrative controls and personal protective equipment. The strongest feasible option depends on the task. Administrative measures and PPE can be necessary but should not become the default alternative to addressing a hazard at source.
Translate assessments into field arrangements such as permits to work, verified energy isolation and contractor coordination. A matrix sitting in a file does not control the work.
ISO 45001 and Saudi projects
ISO 45001 requires a suitable process for identifying hazards and assessing OH&S risks. Your method must suit the organization and applicable requirements. Major clients can specify additional formats, approval routes and review triggers; confirm the current project documents rather than assuming a universal Saudi scoring matrix.
Common mistakes
- Using broad hazards without identifying who may be harmed and how.
- Scoring proposed controls as if they were already operating.
- Adjusting numbers merely to reach an acceptable color.
- Ignoring catastrophic scenarios or interaction between tasks.
- Failing to review after change, control failure or an incident.
Frequently asked questions
How often should an assessment be reviewed?
At planned intervals and when relevant conditions change, new information becomes available, or an incident indicates the assessment may no longer be adequate.
Is a score of 5 automatically acceptable?
No. Acceptance depends on your approved methodology, consequences, legal requirements and authorization rules.
Does ISO require this exact matrix?
No. A 5×5 matrix is one possible tool, not a mandated ISO scoring system.